I think you will have to upgrade your system toolkit versions recursively e.g. you upgrade the system toolkit of your process app and then edit the referenced toolkits which use the older system toolkit to use the newer system toolkit and then create a snapshot and use that in your process app, you can have a toolkit referencing a toolkit also so you will have to go to all the levels and do the same.