0 votes
63 views
in Activities & Tasks by (150 points)
Hi,

I have loan approval process. For activity "Aprove Loan" there are several users who must complete this task.

How can I collect this approvals without dublication activities?

1 Answer

0 votes
by (480 points)
selected by
 
Best answer
Hi Manana,

I think you can use the multiple-instance loop and assign to each user. Otherwise, I dont think multiple users can work on a task.

Thanks,
Tung
by (150 points)
Thanks Tung, I'll try it.

Related questions

0 votes
0 answers 165 views
0 votes
0 answers 38 views
0 votes
2 answers 574 views
0 votes
1 answer 356 views
0 votes
0 answers 57 views
asked Jul 11 in Integrations by Abhishek (120 points)
0 votes
0 answers 54 views
0 votes
1 answer 394 views
asked Jan 4, 2019 in Portal by anonymous
+1 vote
2 answers 583 views
asked Dec 1, 2018 in BPD by anonymous
0 votes
1 answer 284 views
0 votes
2 answers 644 views
asked Aug 31, 2018 in BPD by anonymous
+1 vote
8 answers 2.1k views
asked Jun 11, 2018 in BPD by anonymous
0 votes
2 answers 569 views
asked May 28, 2018 in BPD by anonymous
0 votes
2 answers 830 views

589 questions

485 answers

90 comments

1.8k users

Dosvak IBM BPM /BAW Products, Download Evaluation
Process & Performance Tools Process & Performance Tools
Code Analyzer Code Analyzer
UI Toolkit UI Toolkit
Integration Monitoring Integration Monitoring
Welcome to BPM Tips Q&A, Community wiki/forum where you can ask questions and receive answers from other IBM BPM experts and members of the community. Users with 2000 points will automatically be promoted to expert level.
Created by Dosvak LLC
Our Youtube Channel
...