0 votes
800 views
in Activities & Tasks by (190 points)
Hi,

I have loan approval process. For activity "Aprove Loan" there are several users who must complete this task.

How can I collect this approvals without dublication activities?

1 Answer

0 votes
by (860 points)
selected by
 
Best answer
Hi Manana,

I think you can use the multiple-instance loop and assign to each user. Otherwise, I dont think multiple users can work on a task.

Thanks,
Tung
by (190 points)
Thanks Tung, I'll try it.

Related questions

+1 vote
1 answer 2.4k views
0 votes
0 answers 521 views
asked Feb 13, 2021 by Manana (190 points)
0 votes
0 answers 656 views
0 votes
2 answers 1.8k views
0 votes
1 answer 1.2k views
0 votes
0 answers 373 views
0 votes
0 answers 993 views
asked Jul 11, 2020 in Integrations by Abhishek (120 points)
0 votes
0 answers 192 views
0 votes
1 answer 1.2k views
asked Jan 4, 2019 in Portal by anonymous
+1 vote
2 answers 1.7k views
asked Dec 1, 2018 in BPD by anonymous
0 votes
1 answer 848 views

634 questions

495 answers

97 comments

2.7k users

Join BPM Community Discord Channel

Welcome to BPM Tips Q&A, Community wiki/forum where you can ask questions and receive answers from other IBM BPM experts and members of the community. Users with 2000 points will automatically be promoted to expert level.
Created by Dosvak LLC
Our Youtube Channel
...